Phase 3 & 4 Extensions: Phase 1 2018, Phase 2 2020 Extensions at Takumi Precision Engineering Ltd with a floor area of 1,183 m2 (12,700 ft2), external hard and soft landscaping and all associated site works as per the Architect’s and Engineer’s Read More
The works comprise clearance of existing site structures, overgrowth etc and the construction of a proposed Heavy Goods Sales & Servicing Facility with ancillary staff accommodation, standalone environmental shed and associated site services, hard standing, boundary works and landscaping. The gross floor Read More
Abbey Street Redevelopment: Stage 2 Currently (Feb 2025) Construction of a four storey commercial building comprising shell and core to retail space and partial fit-out to office space together with public realm, boardwalk and site development works. Approx €19m Employer: Ennis 2040 Read More
Phase 1 – Approx €2m Refurbishment & Upgrade Works at Dunnes Stores, Douglas Court Shopping Centre, Douglas, Cork. The project involves demolition and strip-out works, including lift installation, mezzanine floor installation and services installation/upgrade works as detailed in the Architect’s, Engineer’s, Services Read More
Works to Existing Fuel Station at Estuary Fuels, Main Street, Foynes, Co. Limerick The project involves the demolition of existing buildings, construction of new buildings, replacement of external concrete surfaces along with works to below ground services. Client: East Cork Oil Company Read More
The works comprise of the demolition of the common over-flow carparking area to facilitate the provision of a light industrial facility with ancillary office space, yard space, refuse stores, carparking, bicycle parking, ESB sub-station, switch room and associated site works Other works Read More
The project involved the demolition and removal of the existing office fit out including all mechanical and electricial services. A full re-fit of the building was then undertaken in line with the clients new design for the office layout. A new mechanical Read More
E.I Electronics Office & Production Building Project: The project involved the demolition of an existing service yard and carparking area in order to facilitate the construction of a two-storey extension to the existing production facility, along with office, entrance foyer and R&D areas Read More
Blocks K&L, Shannon Free Zone This project involved the construction of 3 No. large scale light industrial units on the footprint of the original industrial/office units which had been demolished. The project entailed the design of the development with associated provision for Read More